Parking Lot Roadwork

The City of Mississauga team at Paramount Fine Foods Centre will be working through an ongoing site improvement project, which includes resurfacing and paving roadways and parking lots at the Centre.

This project will begin on July 24th, and continue in phases through until September 2024. Please note that these dates are subject to change depending on weather conditions and any unforeseen circumstances. Please monitor this page for continued updates.

User groups, tenants, visitors, staff and participants are asked for cooperation and understanding during this time as the construction contractor makes their way through each of the parking lots. Our team here at PFFC is committed to minimizing any inconveniences during this process, and we will provide regular updates to keep you informed of any direct impacts.

Roadwork schedule

Please refer to our facility and parking lot map for location information.

Phase 1 – July 24 to August 21, 2023
  • Parking lots C1 and C2 – July 24 to August 21
  • Parking lots A3 and A4 – August 1 to August 21
  • Roadway from Rose Cherry Place to North end of Sportsplex (Building C)
Phase 2 – August 22 to September 22, 2023
  • Parking lot A1
  • Parking lot A2
  • Parking lots behind Rinks 2, 3, and 4 (loading docks LD2, LD3, and LD4)
  • Roadway from Rose Cherry Place to Rinks loading docks (Building A)
  • B-Arena Gate 3 entrance
Phase 3 – September to October 2023
  • Parking lot C3
  • Parking lot D1
Phase 4 – November 2023
  • Parking lot B3
  • Parking lot B4
  • Building B Loading Dock (LD1)
  • Roadway connecting B4 to LD1
Phase 5 – TBD 2024
  • Parking lot B1
  • Parking lot B2
This site improvement is part of a larger rehabilitation project for Paramount Fine Foods Centre. Learn more about the Paramount Fine Foods Centre Rehabilitation Project.